ENERGY EFFICIENCY IN ELECTRICITY DISTRIBUTION IN THE KUCOVA AREA
§ Path: Albania / Kucova / Sector: Energy efficiency
§ CURRENT STATUS: Project Idea scouted in 2007. Project Idea on stand-by.
The objective of the proposed project activity is to reduce GHG by introducing energy efficiency measures to the Distribution Area of Kucova that supplies electricity to different categories of consumers like households, service, industry and agricultural sector. By increasing energy efficiency in this distribution area, the project activity will generate GHG emission reductions through reducing electricity consumption in this zone.
- Overloading of several 220 kV transmission lines causes losses, lower voltage level than standard and load shedding;
- Lack of system flexibility and the inadequate operation, reduces the reliability and capacity of the transmission system;
- Lack of possibility to operate in an optimal way and non-balancing of the reactive power,
- Many assets of the 220/110 kV substations are old and during the last years the maintenance operations barely existed,
- Limitation of electricity exchange capacity with neighbouring countries,
- The old and inefficient communication means of controlling system.
| Electricity Consumption for the Kucova Distribution Zone (GWh/year) | ||||||||||
| Year | 1996 | 1997 | 1998 | 1999 | 2000 | 2001 | 2002 | 2003 | 2004 | 2005 |
| GWh | 254 | 261 | 273 | 282 | 294 | 311 | 319 | 327 | 336 | 343 |
Based on the strategy for reduction of technical losses, the distribution system plan of Kucova Region has been developed. Following are the measures identified:
- Gradual substitution of 35/10-6 kV system with 110/20 kV system, aiming to substitution of all 110/20 kV transformers at the end of the rehabilitation phase. This will reduce technical losses from 15,8% to 5%. At the same time, approx. 300 transformers with standardized characteristics 20/04 kV, 100 kVA will be constructed and placed in pillars in rural zones, resulting in reduction of technical losses. Existing transformers in urban zones will be modified from 10-6 kV to 20 kV and new standardized 20/04 kV ones will be adjusted with underground cables, with a capacity of 400 kVA, in order to have impact in reduction of technical losses;
- Installation of electric meters for all consumers categories.
Applied methodology
GHG offset
It is estimated that the project has a capacity to avoid emission of approximately 174.000 tCO2eq for the period 2008-2018.
Sustainability
The project contributes to the sustainable development by increasing efficiency in the electricity distribution and by mitigating negative effects of technical and non-technical distribution losses.
Current status
Winner of tender process: Acegas-Aps (www.acegas-aps.it) in partnership with Hentec
Estimated investment cost
Total investment needed for reduction of technical losses is approximately 7.5 millions EUR.
Local Partners
Kucova Distribution Zone, KESH (Albanian Power Company)